Paint is dry, tiles are set, and now the carpenters have moved in. Building 1 is entering its most personal phase yet, while Building 2 reaches up toward its second floor. Here's where things stand.
Building 1
~97%
Building 2
~60%
Building 3
~16%
Pool Club
~78%
01
Building 1 — the carpenters have arrived at Casa Pisces
Painting is complete. Both inside and out, Building 1 now wears its finished colors — and with that chapter closed, the focus has shifted entirely to the interior woodworking. Carpenters are actively building out the rooms: closets, storage, and corner moulding are being crafted and fitted, piece by piece.
This is the stage that separates a well-built space from a truly well-considered one. Moulding, joinery, and built-in storage are details that guests may not consciously notice — but they absolutely feel. A closet that's the right depth. A corner that's clean and crisp rather than roughly finished. Storage that actually makes sense for how people live out of a suitcase. These are the decisions being made right now, and they matter more than most people realize.
A craft worth mentioning
Why woodwork is the soul of a room
In the tropics, wood does something to a space that no other material quite replicates — it brings warmth against stone and tile, texture against painted walls, and a sense of permanence that feels hand-made rather than assembled. The built-ins going into Building 1's rooms aren't afterthoughts; they're part of the room's character. When guests open a closet or run a hand along a finished corner, that's the craftsmanship they're meeting.
✓ Tiling — complete throughout
✓ Interior & exterior painting — complete
✓ Doors & windows — installed
→ Interior woodwork — closets, moulding & storage underway
→ Fixtures, furniture & final sign-off
What's next
Once the woodworking is complete, the final installations — furniture, fixtures, and finishing touches — are all that remain before Building 1 is ready to welcome its first guests.
02
Building 2 — Casa Pisces is heading upward
Building 2 has now completed every wall on the first floor — both the outer shell and all interior room-dividing walls are fully in place. The structure is solid, the layout is defined, and the building is ready to grow. The casting of the second-floor cement slab is actively underway, which means the ceiling of the first floor and the foundation for the second floor are being formed right now.
It's a pivotal moment. Once that slab is poured and cured, the second floor becomes the new frontier — walls going up, rooms taking shape, and Building 2 stepping into the same finishing journey that Building 1 is now deep in. The pace has been consistent and strong, and there's every reason to expect the second floor to rise just as quickly as the first.
✓ Foundation poured
✓ All first-floor outer & inner walls — complete
→ 2nd floor cement slab — being cast now
→ 2nd floor walls — coming very soon
→ Interior finishes — tiling, painting, woodwork
What's next
The slab pour will be followed almost immediately by second-floor wall construction. By the next update, Building 2 should be visibly two stories tall.
Building 1 is within touching distance of completion. Building 2 is about to reach its full height. Every update we write, the picture of Casa Pisces becomes a little clearer — and a little closer to the day we open the doors for real.
We'll be back soon with what may be our most exciting update yet.